Client: BT Mining
Overview:
BT Mining required a lime storage and dosing plant to provide PH correction to the water runoff from their Stockton Mine.
They required a competent contractor with experience in Lime Dosing Plant design to design and build a dedicated facility on the challenging site.




Solution:
Brightwater were able to draw on previous designs and propose a plant to meet BT’s requirements.
Brightwater were able to provide all the design, fabrication, site installation and electrical installation and automation for the plant.The plant included a 90T silo with dust handling and lime metering, 10m3 batch mixing tank, controlled makeup and dosing along with dedicated MCC room and controls.